transportation
THE BIG PIG: Originally estimated at $420 million, SEPTA's El project has nearly doubled in cost. : Michael T. Regan (CLICK IMAGE FOR LARGER VERSION) |
SEPTA calls its ongoing Market Street Elevated Reconstruction Project "the most important transit project in the U.S." But lately, it could also be deemed an ever-deepening money pit as the transit agency has pushed back completion dates and continued working with companies it has publicly blamed for some of the delays.
The project was originally estimated to cost $420 million. Now, as a two-week shutdown recently ended, that figure has nearly doubled, to $710 million. And originally scheduled for a November 2007 end date, they now expect the project will reach "substantial completion" in December 2008.
"Overall, the project has just been a really big mess," says Michael Nutter, the Democratic candidate for mayor who served as that district's councilman. "There are always things that can be done better. However, with this project, I don't know much of anything that can be done worse."
SEPTA blames an evolving vision of what the line should ultimately look like, and the unpredictable nature of such projects.
"If you look historically at projects that involve rebuilding something that already exists, when you're doing the cost estimates, you can pretty well figure what it's going to cost to build from scratch," says spokesman Richard Maloney. "But when you're tearing down an old structure, you can't always predict what problems you're going to encounter."
That might come as news to West Philly residents who've seen businesses shuttered, streets sullied and their commutes turned nightmarish. "SEPTA did not fully explain the reasons for the delays or cost overruns," Nutter says. "I know that one of the contracts was suspended, and that caused some pretty significant delays. It is always difficult to get complete explanations from SEPTA."
The contract that Nutter referenced involves contractor PKF Mark III, which had a $74 million contract to work on the Cobbs Creek section of the line. SEPTA was not satisfied with their work, and after SEPTA ordered them to stop the work, the companies engaged in lengthy litigation, which recently ended in settlement.
(PKF Mark president Pete Getchell has stated before that, "SEPTA has managed this project so badly that we had no other choice" than to sue to get out of the contract. The company's 2004 suit stated "that SEPTA breached its contract on the Cobbs Creek portion of the project, causing significant delays and overruns.")
Yet today, PKF Mark III continues to work on the El under a second contract: an $89 million arrangement to rebuild the elevated structure along Market Street. Though many have questioned the wisdom of continuing such a relationship, Maloney defends it, saying that it's a reputable company that hasn't botched anything beyond Cobbs Creek.
"They've been on the project all along; it's a big engineering firm, and one that's doing some very good work," he says, noting that there have been no problems with them other than "that one section not getting done right."
For his part, Getchell says, "all our issues with SEPTA have been resolved and we're working on our current contract."
Apart from the widening of the project's scope, the rising prices of fuel, concrete and steel are also regularly cited as problems. Making matters worse is a growing concern about minority contracting.
On its project Web site, SEPTA says it aims to provide business and work to local and minority contractors and workers. "SEPTA set the work-hour goal for minorities to 26.4 percent and established a 10 percent voluntary work-hour goal for residents in the construction area," as well as a goal for 6.9 percent of work hours to be completed by females. SEPTA recently cited 25.9 percent minority work-hour fulfillment, 7.3 percent local participation, and 1.3 percent female participation.
"I always thought their goal numbers were a little low anyway," Nutter says. "I have always been concerned with SEPTA's minority, female and disadvantaged business participation rates."
Pat Gillespie, president of the Philadelphia Building Trades Council, AFL-CIO, was also skeptical of the inclusion numbers, singling out contractors like PKF Mark III.
"They've got an affirmative action program, but apparently it's all white," says Gillespie. When PKF Mark III rehabilitated the Route 15 trolley, "You'd go down Girard Avenue and you'd see five or six white guys on jackhammers. Now maybe their African-American employees were working somewhere else that day, but when you go to SEPTA and complain about a lack of inclusion, they give you a blank stare: 'What do you want me to do about it?'"
Getchell declined to respond to the inclusion comments, saying only, "You'll have to ask Pat what he really means by that."
Meanwhile, weekend El shutdowns will continue every weekend through November.

Let’s face it: SEPTA is not user-friendly. You can’t get change from a real live person, you can’t even buy a token from her. Some subway stops don’t have token machines. Bus stops do not feature posted schedules, how hard can this be? Bus routes serve different neighborhoods in a system that almost demands two or three transfers—which you must pay extra for, unless you hold a Transpass. A Transpass that is not smart enough to deduct fares via a debit system, such as can be found in New York, Boston, Washington, DC, . Consider what kind of vibe this impresses upon the infrequent SEPTA-rider: Fuck you.